September20 , 2026

    Bharatmala Pariyojana Phase 1 total expenditure at Rs 4.10 trn: Gadkari

    Related

    Aznar Shipping Plans Fleet Expansion, Targets P737 Million IPO

    Cebu-based Aznar Shipping Corp. is expanding its RoRo fleet...

    DPA Kandla Undertakes Health, Welfare and Cleanliness Initiatives Under Swachhata Campaign

    Deendayal Port Authority (DPA), Kandla, has undertaken a series...

    DCI Appoints Susanta Kumar Purohit as Additional Director

    Dredging Corporation of India Limited (DCI) has appointed Susanta...

    IIT Madras Team Aritra Wins 2026 Njord Challenge in Norway

    A team of ocean engineering students from the Indian...

    MDL to Invest ₹15,000 Crore in Greenfield Shipyard at Dugarajapatnam

    Mazagon Dock Shipbuilders Ltd (MDL) will invest around ₹15,000...

    Share

    A total expenditure of Rs 4.10 lakh crore has been made under Bharatmala Pariyojana Phase I (BPP-I) as on October 31, 2023, and the difference in actual project cost and normative cost is due to increase in cost of raw material and land acquisition, Parliament was informed on Wednesday.

    In a written reply to a question in the Rajya Sabha, Union Road Transport and Highways Minister Nitin Gadkari said Comptroller and Auditor General (CAG) has made observation about the increase in cost of Phase I of the pariyojana.

    “As on October 31, 2023, the total expenditure (BPP-I) is about Rs 4.10 lakh crore…There has been no diversion of funds from other schemes in the execution of BPP-I,” he said.

    According to Gadkari, certain BPP-I projects were earlier planned under other schemes of Ministry of Road Transport and Highways (MoRT&H) viz, externally aided project (EAP), National Highways Original works NH(O), and SARDP scheme, which were subsequently prioritized under BPP-I as per the network planning.

    “The difference in actual project cost and normative cost under Bharatmala Pariyojana is due to increase in cost of raw material, increased land acquisition cost, construction of high speed corridors and increase in GST rates etc,” he said.

    In 2017, the Cabinet Committee on Economic Affairs (CCEA) approved BPP-I entailing development of 34,800 km of National Highway corridors with total outlay of Rs 5.35 lakh crore.

    “This was based on the normative cost and not on the basis of detailed project reports (DPRs) of national highways proposed under Bharatmala Pariyojana.

    “DPRs were prepared subsequently and approval of competent authority was obtained for each project,” Gadkari said.