    Dalian Shipbuilding Delivers 16,000-TEU LNG-Powered Boxship 135 Days Ahead of Schedule

    Related

    V.O. Chidambaranar Port Records 32.27% Growth in Coastal Cargo Handling

    V.O. Chidambaranar Port Authority (VOC Port) has registered an...

    CMA CGM Adds Hazira to Weekly Pakistan Khalifa Express 2 Service

    CMA CGM is expanding its west coast India coverage...

    Swire Shipping Cuts Feeder Surcharge on Indian Subcontinent Routes

    Swire Shipping has announced a reduction in its Feeder...

    MSC Strengthens Regional Connectivity with Launch of Two New Services

    Mediterranean Shipping Company (MSC) is strengthening its regional shipping...

    Caerus Shipping Introduces Direct Shipping Service Between Oman and India

    Caerus Shipping has launched its Arab Sea Express (AXS)...

    Share

    China’s Dalian Shipbuilding Industry Co. (DSIC) has delivered a 16,000-TEU LNG dual-fuel container vessel to Minsheng Financial Leasing, completing the handover 135 days ahead of the contractual deadline.

    The vessel, named MSC Marianna XVI, was delivered on November 16 at DSIC’s Tianjin shipyard. It was built by DSIC’s Tianjin subsidiary in cooperation with China Shipbuilding Trading Co. (CSTC) and will be chartered to Switzerland-based Mediterranean Shipping Company (MSC).

    The Liberia-flagged vessel has a capacity of 16,196 TEUs and measures 366 metres in length, 51 metres in breadth and 30.2 metres in depth. Its design incorporates LNG dual-fuel propulsion technology alongside energy-saving and hydrodynamic drag-reduction systems.

    The vessel’s propulsion and efficiency features are designed to reduce fuel consumption and emissions of sulphur oxides, nitrogen oxides and carbon dioxide. It also meets IMO Tier III emission standards.

    Accelerated construction and commissioning

    DSIC reported significant improvements in construction efficiency during the project. A key construction phase was completed in 284 days, 76 days faster than the shipyard’s standard production cycle.

    The afloat installation and commissioning stage took 75 days, nearly a month less than the time required for earlier vessels in the series. The achievement established a new production record for the Tianjin facility.

    The delivery follows the handover of another 16,000-TEU LNG dual-fuel container vessel, MSC Viola, which DSIC’s Tianjin operation delivered to Minsheng Financial Leasing in January 2025.

    The latest delivery highlights the Chinese shipbuilder’s expanding capabilities in constructing large LNG-powered container vessels and improving production efficiency. It also reinforces the collaboration between DSIC, CSTC and Minsheng Financial Leasing in the large containership segment.