September14 , 2026

    Halwara International Airport set for AAI handover within a month

    Related

    Kottayam Port Commences First Container Movement to Vizhinjam

    Kottayam Port has commenced its first container movement to...

    Paradip Port Handles 17,279 Tonnes of New Steel Beam Cargo

    Paradip Port Authority (PPA) has added 17,279 tonnes of...

    NMHC Lothal Project Progress Reviewed at Governing Council Meeting

    Union Minister for Ports, Shipping and Waterways Shri Sarbananda...

    Kamarajar Port Begins IPO Process, Targets Public Listing by 2027

    Kamarajar Port Ltd, India’s first corporate major port, has...

    Oman Ship Attack Leaves One Indian Seafarer Missing, 13 Rescued

    One Indian seafarer remains missing after a ship was...

    Share

    The process of transferring the under-construction Halwara International Airport to the Airports Authority of India (AAI) is on, with officials expecting the handover to be completed within a month. The public works department (PWD), which oversaw the airport’s construction, is conducting final checks before AAI takes control and begins operational preparations.

    A PWD official confirmed that the transfer process had started last week. The official said: “We are reviewing various services, including public health systems, electrical infrastructure, and fire safety measures. Since AAI is responsible for making the airport operational, they need to verify these systems before taking full control.” PWD sources claim that the handover is expected to be finalised by mid-April. Once completed, AAI will begin obtaining the permissions to commence airport operations.

    The terminal building has been completed, with key systems such as air conditioning, baggage handling, and lighting already functional. Officials noted that furnishing work will be done just before operationalisation to prevent dust accumulation.

    One of the final tasks is the carpeting of the runway, which is set to begin this week and should be finished by mid-April. “Runway work requires specific temperature conditions, and March is the ideal time for this,” an official explained. The last layers of Link Taxi Tracks 1 and 2 will also be laid this month, and a trolley gate has already been installed.

    An AAI official confirmed that: “Minor finishing tasks remain. AAI is coordinating with the PWD and the Air Force to expedite the airport’s readiness.

    Residents are eager for the launch. Local resident Mandeep Singh said:. “It will benefit region’s traders, industrialists, professionals, students, and travellers.”