August5 , 2026

    Iraq’s Faw Port to connect to submerged tunnel by next month

    Related

    PIL Strengthens India–East Africa Trade with Launch of Weekly Imara Express Service

    Pacific International Lines (PIL) has announced the launch of...

    Indian-Flagged Vessel Sinks After Attack Off Yemen; All 13 Indian Crew Rescued

    An Indian-flagged merchant vessel, MSV Faize Noore Oliya, came...

    V.O. Chidambaranar Port Records 106.55% Growth in Windmill Blade Cargo Handling

    Reinforcing its position as a key facilitator of India's...

    CONCOR Launches Import Loaded Reefer Movement Facility at ICD-TKD

    Container Corporation of India (CONCOR) has operationalised Import Loaded...

    Share

    Work on completing the road link between Iraq’s Faw Port and a submerged tunnel will be completed by February.

    The road is 51 km long and will be completed 100 percent by next month, Iraq News Agency reported, quoting Farhan Al-Fartousi, Director General of state-run General Company for Ports.

    He said work on the other sections of the connecting road is proceeding at a good pace, with completion rates reaching more than 98 percent on Bridge No.1 and Bridge No.2, which are part of the road project.

    Work on the underwater tunnel will start soon, Al-Fartousi said.

    In November 2024, the General Company for Ports announced the handover for five berths at the Grand Faw Port in Basra.

    Nasser Al-Asadi, Transport Affairs Advisor to the Iraqi Prime Minister confirmed in the same month that negotiations were continuing with UAE’s AD Ports Group to take on the management and operation of the Grand Faw Port.