July27 , 2026

    Trial run of cargo operations at Vizhinjam from May onwards

    Related

    VOC Port Reports 11.8% Growth in Berth Productivity During Apr–Jun FY 2026–27

    V.O. Chidambaranar Port Authority (VOC Port) recorded a significant...

    Vizhinjam Seaport Gets Customs Nod to Launch EXIM Cargo Operations from August 18

    Vizhinjam International Seaport has received final approval from the...

    Adani Ports Plans 100-Acre CFS at Vizhinjam as Exim Operations Begin

    Adani Ports and Special Economic Zone (APSEZ) plans to...

    Four Indian Crew Members Aboard Vessel Struck at Odesa Port; Two Confirmed Safe

    A merchant vessel carrying four Indian nationals was struck...

    Adani Ports Posts 9% Rise in Container Throughput

    Adani Ports and Special Economic Zone (APSEZ) reported a...

    Share

    The trial run of cargo handling operations at Vizhinjam International Seaport will commence by the end of May 2024.

    Yard and ship-to-shore cranes brought to the port from China will be used to carry out the operations of loading and unloading cargo from two container ships on a trial basis. The port company officials revealed that they had made the necessary arrangements, including appointment of technical experts, to conduct the trial run.

    The port requires 32 cranes, including 24-yard cranes and eight ship-to-shore cranes. The cranes have been brought to the port from China since last August.

    Along with this, Zhenhua-35 (a Chinese heavy load carrier ship), which came back from China with cranes, reached the outer sea with four-yard cranes and two ship-to-shore cranes. After receiving all necessary approvals, the ship was allowed to dock with the help of the technical team.

    The authorities said that the port is now equipped with 20-yard cranes and six ship-to-shore cranes. The required four-yard cranes and two shipto-shore cranes will be delivered by the second week of May.