    Vizhinjam port: Breakwater a reality despite multiple setbacks during construction

    Related

    Iran Claims Supertanker Carrying Over 2 Million Barrels of Oil Sunk in Strait of Hormuz

    Iran's Islamic Revolutionary Guard Corps (IRGC) has claimed that...

    Jiangnan Shipyard Delivers Second 14,000 TEU ‘Kun’ Series Container Ship to MSC

    Jiangnan Shipyard, a subsidiary of China State Shipbuilding Corporation...

    TCI Strengthens Coastal Shipping Operations with Two Additional Ships

    Transport Corporation of India (TCI) has expanded its coastal...

    MSC Boosts Red Sea Connectivity for North Indian Exporters

    Mediterranean Shipping Company (MSC), the world's largest container shipping...

    Share

    A major milestone has been reached in the development of Vizhinjam Port with the completion of its breakwater.

    The breakwater, a structure designed to protect the port’s berth from waves by placing stones in the sea, is now a reality.

    For the 2,950-metre-long breakwater, 7 million tonnes of granite stones were deposited in the sea, placed at depths ranging from 14 to 20 metres.

    At the base, the stones cover an area of 100 to 120 metres, tapering to about 10 metres wide at the top. This large triangular wall will serve as a protective shield for the port.

    Construction of the breakwater began in 2016 and, over the past eight years, has overcome various challenges, including climate change.

    Initially, Cyclone Ockhi caused significant disruptions, destroying part of the breakwater. Later, a shortage of rocks was resolved by sourcing stones from quarries in Kerala and Tamil Nadu.

    The majority of the breakwater was constructed between 2021 and 2024. Due to unfavorable sea conditions during the monsoon, construction was only possible from October to April each year. In 2022-23, work was halted for 120 days due to protests by fishermen.

    Loading points were established in Kollam and Muthalapozhy to collect the stones, which were then transported to the placement site via barges.

    At Vizhinjam, stones were gathered at three points. Tipper lorry trucks and barges transported the stones, with barges used for placement in areas deeper than 5 metres, while lorries were used to place stones above them. A total of twelve barges were deployed for the construction.

    In the upcoming phase, accropode will be laid around the breakwater to provide additional protection. A 10-metre-wide concrete road will also be built on top of the breakwater. Similarly, an additional 900 metres of breakwater will be constructed in next phase, extending its total length to 3.9 kilometres. No other port in the country boasts a breakwater of 2.95 kilometres constructed at such depths.