    HC directs NHAI to slash toll fee by 80% on under-construction NH44 stretch

    Related

    Government Scraps Immigration Procedures for Indian Crew on Coastal Vessels

    The government has scrapped the requirement for immigration procedures...

    Gujarat Pipavav Port Q1 FY27 Net Profit Rises 42% to ₹148 Crore

    Gujarat Pipavav Port Ltd, which operates Pipavav Port in...

    CSL Delivers Second HS EcoFreighter to German Shipowner

    Cochin Shipyard Limited (CSL) on Wednesday delivered the second of...

    Chennai Port Strengthens Rail Connectivity to Hinterland Markets

    Chennai Port Authority is stepping up efforts to strengthen...

    Deendayal Port Moves Ahead with Tuna-Tekra Road Link Project

    Deendayal Port Authority has advanced the road connectivity plans...

    Share

    In a key judgment, the Jammu and Kashmir and Ladakh High Court has directed the National Highways Authority of India (NHAI) to reduce toll charges by 80 per cent at two toll plazas on the Pathankot-Udhampur stretch of NH-44 due to poor road conditions and ongoing construction.

    Toll cut ordered at Lakhanpur and Bann plazas

    A division bench of Chief Justice Tashi Rabstan and Justice M A Choudhary, while hearing a Public Interest Litigation (PIL), ordered NHAI to collect only 20 per cent of the existing toll charges at Lakhanpur and Bann plazas. The order is effective immediately and will remain in force until the highway is fully operational.

    The court observed that commuters cannot be expected to pay full tolls when the road infrastructure is damaged or incomplete. “Tolls are meant for providing quality road infrastructure. If the road is in poor condition, it is unfair to continue full toll collection,” the court said.

    The court also ruled that no toll plaza should be set up within a 60-km stretch on the highway. It directed that existing toll plazas violating this norm in Jammu and Kashmir and Ladakh be removed within two months.

    The bench noted that there should not be a “mushrooming of toll plazas” in the Union Territories with the sole purpose of revenue generation at the expense of the public.

    The PIL, filed by Sugandha Sawhney, stated that 60 to 70 per cent of the Pathankot-Udhampur highway has remained under construction since December 2021. Despite that, toll collection continued, in violation of guidelines which state that tolling should begin only within 45 days of project completion.

    Highway reduced to single lane: NHAI
    The court took note of NHAI’s submission that large sections of the highway have been reduced to a single lane due to construction work. It also observed the presence of potholes, diversions and damaged stretches that hinder safe travel.

    The court referred to Union Road Transport and Highways Minister Nitin Gadkari’s remarks at a global workshop in June 2024, where he said, “There is no justification for charging toll if roads are not in good condition.”

    The court’s ruling is expected to set a precedent for similar cases where highways remain under construction and tolls are collected in full. NHAI will now be required to align toll collection with actual road conditions.