May2 , 2026

    J M Baxi heavy archieves landmark feat: Delivers heaviest modules ever for L&T Marjan offshore project

    Related

    Kamarajar Port Sets New Container Handling Record with Maersk Vessel

    In a significant boost to India’s maritime efficiency, Kamarajar...

    Labour Day Boost: Rajkot Tribunal Delivers Landmark Relief to Kandla Port Workers

    In a landmark development coinciding with International Labour Day,...

    124 Villagers Voluntarily Hand Over Land for Vadhvan Port Project in Palghar District

    In a significant development for India’s maritime infrastructure expansion,...

    Tuticorin Port and ABB Partner to Develop Shore-to-Ship Power Technology

    V.O. Chidambaranar Port Authority (Tuticorin Port) has entered into...

    Share

    J M Baxi heavy has set a new benchmark in Indian engineering with the successful delivery of three record-breaking modules for Larsen & Toubro’s (L&T) Marjan Offshore Field project .

    Overcoming Challenges, Delivering Excellence

    Despite the disruptions caused by the COVID-19 lockdown in March 2020, J M BAXI HEAVY’s dedicated team persevered, ensuring the flawless fabrication of these colossal structures – named TP-11, TP-12, and TP-13. These modules stand as a testament to India’s prowess in the engineering domain.

    Strategic Planning and Flawless Execution

    The project officially commenced in November 2023, following the navigation of pandemic-related hurdles. J M BAXI HEAVY’s meticulous planning resulted in successful loadouts every 60 days, showcasing their exceptional project management capabilities. Innovative loadout strategies and the implementation of a meticulous float-over operation guaranteed the safe and efficient transportation of these behemoths.

    Breaking Records and Setting New Standards

    J M BAXI HEAVY’s accomplishment culminated on May 30, 2024, with the final loadout of TP-12. These monumental modules, along with their load spreaders and axles, were meticulously transported and loaded using cutting-edge equipment, including 260 SPMT axle lines with 12 Power Pack Units (PPUs) and 85 ballast pumps. Remarkably, each loadout – from axle insertion to final placement onto the HDB-402, a 400-ton float-over barge – was accomplished within a staggering 36 hours.

    With a combined weight of a staggering 18,000 metric tons and encompassing 530,000 freight units, these modules represent a significant leap forward in engineering and logistical prowess.

    Gratitude and Commitment

    J M BAXI HEAVY expresses its deepest gratitude to L&T Hydrocarbon for entrusting them with this momentous project. The company reiterates its unwavering commitment to upholding project timelines and prioritizing safety in every endeavour.

    Name Dimensions

    (LxWxH) mm

    WT. (MT) Qty Load out dates Loadout Wt. (MT)
    TP -11 TOPSIDE 73.67×49.50×47.91 5663 1 03/12/2023 6857
    TP -13 TOPSIDE 73.67×49.50×47.91 6314 1 08/03/2024 7557
    TP -12 TOPSIDE 73.67×49.50×47.91 5554 1 30/05/2024 6786

     

    spot_img