    State extends deadline for Mulapeta port project

    Related

    Rahul Modi Takes Over as Chairman of Indian Maritime Centre

    Mumbai, October 3, 2026: Rahul Modi has taken over...

    TICT Records Highest-Ever Monthly Throughput With 33,771 TEUs in September

    Tuticorin International Container Terminal (TICT) at Berth No. 9...

    DPA Kandla Sets New National Record with 9.64 Lakh MT Cargo in a Day

    Deendayal Port Authority (DPA), Kandla, has achieved yet another...

    Chennai Port Container Terminal Records Decade-High Handling in September

    Chennai Container Terminal Pvt. Ltd. (CCTPL), operated by DP...

    JNPA, Maharashtra Government Explore Electric Freight Mobility

    Jawaharlal Nehru Port Authority (JNPA), the Transport & Ports...

    Share

    The state government approved a 409-day extension for the Mulapeta Greenfield Port project, allowing completion by 30 November 2026 without imposing liquidated damages on the contractor.

    The extension was granted following delays beyond the contractor’s control. These included adverse weather, cyclone events, government restrictions on minor minerals, site access issues, and delays in handing over encumbrance-free land for external infrastructure. Phase-I of Mulapeta Port, formerly known as Bhavanapadu Port, was sanctioned on 17 August 2021 with a total project cost of Rs. 4,361.91 crore under the landlord model. The project was awarded to Viswa Samudra Ports (JV), Hyderabad, on August 2, 2022 at a contract value of Rs 2,949.70 crore, with an original completion date of 17 October 2025. Key components include breakwaters, dredging, berthing structures, onshore infrastructure , external roads, rail connectivity, and power and water supply.

    As of October 2025, physical progress stood at 60.49 per cent, and financial progress at 56.28 per cent. Following a comprehensive assessment by TCE Ltd., the project management consultant recommended the extension due to unavoidable delays.

    The EPC contractor has provided an undertaking stating they will not claim additional costs due to the extension, while retaining their contractual rights.