August27 , 2026

    Presentation on CAG’s Bharatmala Pariyojana report made to PAC

    Related

    Gujarat Weighs Concession Extensions for Major Private Ports

    The Gujarat government is understood to be considering an...

    Paradip Port Signs 30-Year Concession Agreement for Kalinga Bulk Terminal

    Paradip Port Authority has signed a Concession Agreement with...

    MNRE Additional Secretary Visits V.O. Chidambaranar Port to Review Green Energy Initiatives

    V.O. Chidambaranar Port Authority (VOCPA) welcomed Shri Mayank Tewari,...

    Delta Ports Mormugao Terminal Records 37,405 MT Loading Performance

    Delta Ports Mormugao Terminal Pvt. Ltd. has achieved a...

    Indian Ports, Airports Prepare for Foreign Cargo Diverted by Hormuz Crisis

    India is preparing its ports and airports to handle...

    Share

    A presentation of the recent CAG report on the ‘Bharatmala Pariyojana’ was made at a meeting of the Parliament’s Public Accounts Committee headed by Congress MP Adhir Ranjan Chowdhury on Tuesday, sources said. The audit report on the implementation of Phase-I of the ‘Bharatmala Pariyojana’ highway projects triggered a political row with opposition parties alleging corruption in the process of awarding the project.

    The Road Transport and Highways Ministry, however, has said the Comptroller and Auditor General’s (CAG) findings that the cost was exorbitant are misplaced as it did not factor in the actual cost.

    The sources said at the PAC’s meeting on Tuesday, there was a presentation on the CAG report, which was tabled in Parliament on August 10.

    The PAC is a committee of selected MPs that audits the revenue and expenditure of the government, and its primary function is to examine a report of the CAG after it is tabled in Parliament.

    During the meeting, they said, opposition members raised concerns after the ‘Bharatmala Pariyojana’ report’s presentation.

    However, the report will not be taken up for examination immediately.

    According to procedure, after tabling of the report, the Road Transport and Highways Ministry was given 30 days to furnish a draft Action Taken Note to the CAG, after which the auditor will get another 30 days to vet the replies and seek further clarifications from the ministry. The report will be examined by the PAC once the process is over.

    The PAC also selected additional subjects, including welfare schemes announced by the government, for examination of status and money spent, the sources said.

    The panel will also examine the banking and insurance sector, which will include loans given and Non Performing Assets. Another subject which will be examined by the committee is the reforms in the energy sector, they said.