    Railways’ eastern freight corridor to be fully operational by next month

    Related

    Chennai Port Launches HAIAN Lines’ Monthly CVI Container Service to Vietnam

    Chennai Port has commenced HAIAN Lines’ new monthly CVI...

    India Moves to Reopen Mogalhat Land Port Through Talks

    The Indian government is preparing to initiate discussions with...

    NITI Aayog Vice Chairman Dr. Ashok Kumar Lahiri Visits Paradip Port

    Paradip Port Authority accorded a warm welcome to Dr....

    ICS Madras Holds AGM 2026 and Panel Discussion on Maritime Risks

    The Madras Branch of the Institute of Chartered Shipbrokers...

    India and Cyprus Hold First Joint Maritime Committee Meeting in Limassol

    India and Cyprus have taken a significant step towards...

    Share

    The full-fledged operation of the 175.1-km section from Sahnewal in Punjab to Pilkhani in Uttar Pradesh of the Eastern Dedicated Freight Corridor will start next month.

    The project was divided into three parts — Sahnewal to Shambhu in Punjab, covering 81.6 km, Shambhu to Kalanaur in Haryana, covering 76.7 km, and Kalanaur to Pilkahni in Uttar Pradesh, covering 16.8 km.

    While the work in Punjab and Uttar Pradesh has been covered as phase-1 and phase-2, respectively, the work in Haryana is being carried out as phase-3 of the project.

    Speaking to mediapersons, Pankaj Gupta, Chief General Manager (CGM), Ambala unit, Dedicated Freight Corridor Corporation of India Limited, said: “The trial phase has been completed. While the tracks and bridges are ready, two traction power substations for power supply were commissioned for the project in Jagadhri and Khanna. We will not be depending on the Northern Railways for power, rather the Meerut unit of the project is getting supply from the Jagadhri substation.”

    “The operations between the Shambhu to Sahnewal section of the freight corridor and the Kalanaur to Pilkhani section will be started in November, and then the Shambhu to Kalanaur section will start operations from December due to the ongoing signaling work,” Gupta said.

    The CGM informed that the project under the Ambala unit is being completed at a cost of Rs 5,500 crore. A total of 15 footover bridges were to be built, of which six have been built and the remaining are in an advanced stage and the work will be completed in the next three months. There were 55 level crossings, of which six are pending.