Bangladesh’s Summit LNG said on Thursday it expects to complete repositioning and reconnecting work on its floating storage and regasification unit (FSRU) by August-end, assuming favourable weather and sea conditions.
Ship-to-ship transfer operations at its FSRU are expected to be ready in September, Summit said.
Summit LNG had paused operations on the FSRU after it was damaged by a steel structure when Cyclone Remal lashed Bangladesh in late May, and it declared force majeure on LNG deliveries.
The FSRU was then sent to Singapore for repairs.