July27 , 2026

    Cochin Shipyard reveals updates on new mega dry dock

    Related

    VOC Port Reports 11.8% Growth in Berth Productivity During Apr–Jun FY 2026–27

    V.O. Chidambaranar Port Authority (VOC Port) recorded a significant...

    Vizhinjam Seaport Gets Customs Nod to Launch EXIM Cargo Operations from August 18

    Vizhinjam International Seaport has received final approval from the...

    Adani Ports Plans 100-Acre CFS at Vizhinjam as Exim Operations Begin

    Adani Ports and Special Economic Zone (APSEZ) plans to...

    Four Indian Crew Members Aboard Vessel Struck at Odesa Port; Two Confirmed Safe

    A merchant vessel carrying four Indian nationals was struck...

    Adani Ports Posts 9% Rise in Container Throughput

    Adani Ports and Special Economic Zone (APSEZ) reported a...

    Share

    Cochin Shipyard (CSL) has shared a new image highlighting the substantial progress made on its enormous new dry dock. This cutting-edge facility is nearing completion and is set to
    revolutionize India’s shipbuilding and ship repair capabilities.

    A significant part of the project’s advancement involves the installation and commissioning of a massive 600-tonne gantry crane. This powerful crane will be crucial for managing the large vessels that the dry dock is intended to accommodate.

    CSL expects the new dry dock to be fully operational by August 2024, following the completion of the gantry crane installation and commissioning. The core civil works for the dry dock, such as the dock floor, dock wall, caisson gate, pump house, and sub-stations, have already been successfully finished. The Prime Minister’s official inauguration in January 2024 marked a significant milestone for the project.

    With its impressive dimensions of 310 metres in length, 75/60 metres in width, and 13 metres in depth, the new dry dock will be the largest in India. This stepped dry dock design offers additional flexibility to accommodate a wider variety of vessels.

    The dry dock is designed to last, with a lifespan of 100 years, ensuring that CSL can utilize this critical infrastructure for many generations.

    The exceptional size and capabilities of the new dry dock make it suitable for servicing a diverse range of vessels, including Liquefied Natural Gas (LNG) vessels, aircraft carriers, jack-up rigs, drill ships, large tankers, and merchant vessels, with a draft (depth submerged) of up to 9.5 meters.