    NHAI’s ₹18,885 Crore BOT Highway Projects Fail to Attract Bidders

    Related

    Textiles Ministry Unveils Roadmap to Triple Exports to $100 Billion by 2030

    The Ministry of Textiles has launched a two-day national...

    India-US Trade Surplus Narrows 17% as Imports Surge Ahead of BTA Talks

    India's merchandise trade surplus with the United States narrowed...

    RITES Set to Resume Bangladesh Rail Coach Exports; First Rake Ready in July

    India is poised to resume passenger coach exports to...

    NHAI Partners with NCAER to Establish India’s First Transport Economics Research Centre

    In a landmark initiative to strengthen evidence-based policymaking in...

    Share

    The National Highways Authority of India (NHAI) has failed to attract any bidders for three major highway projects worth ₹18,884.69 crore under the Built, Operate and Transfer (BOT) toll model in Maharashtra and Gujarat, marking a setback to its strategy of reviving the model.

    The projects, covering a total length of 912.3 km, were tendered in three packages. However, despite multiple extensions of the bid submission deadlines and revisions to concession agreements aimed at reducing investor risk, no proposals were received.

    This development comes as NHAI seeks to scale up the BOT toll model while slowing down projects under the Hybrid Annuity Mode (HAM), which had gained popularity among developers due to its lower risk profile since its introduction in 2015.

    Key Projects with No Takers
    Gujarat Corridor: Construction of a 105.8 km six-lane access-controlled highway along the Sanchore–Tharad–Deesa–Mehsana–Ahmedabad stretch, estimated at ₹3,739.69 crore.
    Maharashtra Package I: Development of a 152 km six-lane highway between Adgaon and Ahilyanagar, along with operation and maintenance (O&M) of 133.5 km of the Nashik–Ahilyanagar stretch, costing ₹6,890.55 crore.
    Maharashtra Package II: Construction of a 222 km highway from Ahilyanagar to Hasapur and O&M of 299 km of existing highway stretching from Ahilyanagar to Akkalkot, valued at ₹8,254.45 crore.
    Industry Concerns Persist

    According to Praveen Sethia, Founder and Director of Infrastructure Advisors, the lack of participation highlights a disconnect between policy design and market expectations.

    He noted that while NHAI introduced risk mitigation measures, they may not have fully addressed concerns from a developer’s perspective. He suggested that a more consultative and calibrated approach would be needed going forward.

    Developers also pointed to limited time for due diligence, as key clarifications from NHAI were issued only in January, leaving insufficient time to evaluate project viability.

    Challenges with BOT Model

    Under the BOT toll model, private developers finance, construct, and operate highway projects, recovering investments through toll collection over a concession period.

    However, the model has lost favour in recent years due to persistent challenges, including:

    Delays in land acquisition
    Environmental clearance hurdles
    Traffic volatility affecting toll revenues

    The absence of bidders for these projects underscores the continued hesitancy among private players and signals the need for further reforms if the BOT model is to regain traction in India’s highway development programme.